| Young also updated us on solar projects being developed to feed into BEL's grid.
As we reported, Caribbean International Brewery recently broke ground on a major 14-megawatt Solar Interconnection Project in La Democracia.
They expected it to come online in December, but that's been postponed due to delays in getting the transformers.
In the meantime, though, BEL is paying roughly $2 million a month under a six-month rental contract to keep temporary diesel generators on standby at its Westlake facility. Young explained that those generators have assisted significantly with preventing load shedding:
Lynn Young, Executive Chairman, BEL
"The temporary generation was rented for six months, and we pay a monthly fee to have them here-I think it's 2 million dollars a month. Whether or not we run it, we pay to just have it here, and then on top of that, when we pass diesel through it, we pay for the diesel, so that's how we get up to 80 cents per kWh running the temporary, but even if we don't run it, we pay $2 million. In the contract, we have an option to renew it for a further six months, but our goal is to try to get in the solar-we have three solar systems we are trying to get in before the six months is up. If we get those in place before the six months is up, then we will not renew the contract for the temporary generation; if we don't get them in time, we may have to extend it, but the solar systems are gonna cost much less than the diesel generation."
Reporter:
"The fact that it got here during the cooler months-I know it was set up in September-the fact that it got here during the cooler months and set up for them, does it mean like money wasted?"
Lynn Young, Executive Chairman, BEL
"Well, no. First of all, we had expected it to be in place for the hot month-May, June-but the war created all kinds of logistics, so it got delayed significantly. Some of the equipment was coming in from the Middle East, so you can imagine shipping stuff out of the Middle East became a problem. But it came just when CFE was at its height of curtailment, so if it had come one month earlier, we would have avoided all that load shedding. But it has avoided significant amount of load shedding, and we run it significantly now because during the peaks, CFE is still very expensive. So it's saving us a lot of money from having to buy peak power from CFE."
|